Bucks County Capital Projects

Bucks County Justice Center

Why do we need a new Justice Center complex?
Several issues have necessitated a new Bucks County Justice Center.  When the existing courthouse was constructed, Bucks County had 310,000 residents and four judges. Today, there are 625,000 residents and 13 judges. Since 2005, the number of criminal cases has grown more than 18 percent. In addition, Domestic Relations’ caseload – conducted in cramped quarters at 30 N. Main St – has led to overcrowding in that facility.  The new facility will also provide for improved security measures.

Project Background
In July 2008, Doylestown Borough Council passed four ordinances that permitted the Bucks County Justice Center project to move forward. Final plan approval for phase one, building the new parking garage was granted at that meeting. The next two phases will include demolition of the existing parking garage, and finally, construction of the Justice Center on the site of the existing garage.  In November 2008, by a 2-1 vote (with Commissioners Charles H. Martin and Jim Cawley voting affirmatively, and Diane M. Ellis-Marseglia casting a nay vote), the Bucks County Commissioners approved a $6.57 million contract with design firm Hellmuth, Obata & Kassabaum (HOK) to provide architectural services for the new Justice Center. The architectural contract represented a savings of approximately $5.5 million from a March 2008 proposed contract.  Commissioner Chairman Charley Martin said about the contract, “The desire was to continue, but not at any cost.”

How will the county keep me informed during the project?
The county is committed to keeping all county residents informed throughout the duration of this capital improvement project, the county’s largest-ever.  This page has been created to provide up-to-date information and will soon feature a live Web cam of the construction. You may also sign up on our Web site for e-alerts to receive information when any new information is updated. Bucks County’s Director of Operations Jerry Anderson has met with homeowners and local businesses to discuss construction.  He encourages anyone with questions or concerns to call the General Services Division at 215-345-3949.

Phase 1: Parking Garage
Phase 2: Demolition of existing parking garage
Phase 3: building of the new courthouse

Special Justice Center Newsletters

February 2010 edition
September 2009 edition
January 2009 edition

Justice Center Renderings- January 20, 2010

Click images for larger views

North Side View

Plaza View at Night

Plaza View

Shewell Avenue View

Floor Plans
Stacking Diagram

Parking Garage RenderingPhase 1: Parking Garage

The new garage will feature 1,200 spaces, three elevator towers, three entrances, and a planned security office. The county has kept its commitment to partnering with the borough to ensure an aesthetically pleasing yet functional design.

.Justice Center Construction Web Cam

January 10, 2010 -- Ongoing Installation

Click images for larger views

Capstone
Close up of Capstone.
Stairs in Construction.
Installing Prefabricated Concrete.
Looking down from the top deck.
Completed concrete installation on the second level.
Crane on the top deck.
Exterior view of stairwell.
Exterior view of parking garage.
View from Union Street.
Top parking deck facing the Courthouse.
Exterior view.

 

November 17, 2009 -- Prefabricated Concrete Installation

Click images for larger views

Broad Street View of Construction

HookingColumnToCrane

LiftingColumnWithCrane

MovingColumnInPlace

InstallingColumn

InstallingAColumn

ColumnInstall

ViewNorthTowardsCourthouse

ViewFromRoofOfCourthouse

 

June 1, 2009 -- Construction Progress

Click images for larger views

Doyle Street View of Construction
Construction worker in a manhole
Construction worker down in manhole
Zoomed in view from courthouse roof.
Zoomed out view from Courthouse Roof
View of Old and New Garage
View of Old and New Garage, zoomed out
South wall of new garage
Construction of the garage

 

April 14, 2009 -- Ongoing Construction

Click images for larger views

Bulldozer in action
Construction at the Parking Garage Site

 

February 9, 2009--Early Construction

Click images for larger views

Construction, closer view
Construction, longshot view
Construction, view from the back

 

Groundbreaking December 22, 2008

Click images for larger views

Commissioner Martin
Judge Heckler
Commissioner Cawley
Crowd at groundbreaking
groundbreaking ceremony
2007 parking garage rendering

 

For more information, go to "Bucks County Commissioners, President Judge Break Ground on 1,200-Space Parking Garage: Frigid Kickoff to Phase I of Justice Center Project in Doylestown Borough"

Demolition and Clearing:

Click images for larger views

demolition of houses
Demoltion of garage site
tearing down a house
where the house once stood -- empty clearing
corner of broad and doyle, clear after demolition