Bucks County Capital Projects

Bucks County Justice Center

Special Justice Center Newsletters

Why do we need a new Justice Center complex?
Several issues have necessitated a new Bucks County Justice Center.  When the existing courthouse was constructed, Bucks County had 310,000 residents and four judges. Today, there are 625,000 residents and 13 judges. Since 2005, the number of criminal cases has grown more than 18 percent. In addition, Domestic Relations’ caseload – conducted at 30 N. Main St – has led to overcrowding in that facility.  The new facility will also provide for improved security measures.

Project Background
In July 2008, Doylestown Borough Council passed four ordinances that permitted the Bucks County Justice Center project to move forward. Final plan approval for phase one, the building of the new parking garage (which was completed in June, 2010) was granted at that meeting. Phase two, demolition of the previous County parking garage is complete and phase three includes construction of the new Justice Center on those grounds. In November 2008, by a 2-1 vote (with Commissioners Charles H. Martin and Jim Cawley voting affirmatively, and Diane M. Ellis-Marseglia casting a nay vote), the Bucks County Commissioners approved a $6.57 million contract with design firm Hellmuth, Obata & Kassabaum (HOK) to provide architectural services for the new Justice Center. The architectural contract represented a savings of approximately $5.5 million from a March 2008 proposed contract.  Commissioner Chairman Charley Martin said about the contract, “The desire was to continue, but not at any cost.”

On January 13, 2011, the Bucks County Commissioners voted, two-to-one, to award six contracts for the upcoming $84 million Justice Center project. For more information, please see, "By 2-1 Vote, Commissioners Approve Six Contracts Totaling $84 Million for New Justice Center."

How will the county keep me informed during the project?
The county is committed to keeping all county residents informed throughout the duration of this capital improvement project, the county’s largest-ever.  This page has been created to provide up-to-date information including a live Web cam of the construction. You may also sign up on our Web site for BC Connection, Your Bridge to Bucks Newsletterto receive information when any new information is updated. Bucks County’s Director of Operations Jerry Anderson has met with homeowners and local businesses to discuss construction.  He encourages anyone with questions or concerns to call the General Services Division at 215-345-3949.

Phase 1: Parking Garage
Phase 2: Demolition of existing parking garage
Phase 3: Building of the new courthouse

Phase 3: Justice Center

Justice Center Construction Web Cam

February 2012 - Structural Steel Work (Click images for larger views)

Close up of Armory wall
Cement truck on site Armory wall and crane
Comprehensive view of steel work
Steel rebar
Steel cage
Workers standing on steel rebar
Structural support beams
Support wall for structural work Cement truck and crane
Cement workers
Cement workers

 

November 2011 - Early Foundation Work (Click images for larger views)

Construction site pad with equipment Comprehensive view of construction site Armory
Foundation work   Construction worker leveling foundation

 

September 2011 - Site Work (Click images for larger views)

Construction Continues
Ongoing site work by the armory

 

July 2011 - Site Work & Armory Demolition

Click images for larger views

Profile of Armory in Demolition
Back hoe in rear of Armory
Armory demolition with back hoe
Steel arches from the Armory
More Armory demolition Site work next to Armory Site Pad Construction road from Union Street

 

July 19, 2011 - Groundbreaking Cermony

Bucks County Commissioners joined President Judge Susan D. Scott, county judges and administrators, contractors and local, state and federal elected officials to break ground for the $84 million Bucks County Justice Center. For more information, go to "Commissioners, President Judge Join Doylestown Borough Officials to Break Ground for New Justice Center"

Images (click for larger size)
Commissioner Martin
Director of Operation Jerry Anderson
Mayor Libby White
Commissioners with President Judge, state and local officials
Officials break ground

Groundbreaking Ceremony Audio

June 2011- Construction Update

Click images for larger views

Construction Sign
 
Main Street View
Construction Entrance
Union Street View
Inside Contruction Zone
Construction Zone
Clearing
 
Lower Level
View From above
Armory Building

 

Renderings

Click images for larger views

North Side View

Plaza View at Night

Plaza View

Shewell Avenue View

Floor Plans
Stacking Diagram

The Bucks County commissioners hosted a public forum on February 18, 2010, where Duncan Lyons, architect from HOK, presented proposed plans for the new justice center. Also on hand was Jerry Anderson, director of operations who is overseeing the project. About 75 attendees viewed the plans and had an opportunity to pose questions to Anderson, Lyons, and other officials, including Commissioners Charles H. Martin, chairman, and Jim Cawley, as well as President Judge Susan Scott. To hear a full audio account of the public forum, click here.

Phase 2: Demolition of existing parking garage

December 2010 -- Ongoing Demolition

Click images for larger views

Looking at the existing courthouse
Ongoing Demolition
Demolition Equipment
Hollowed out garage

 

November 2010 -- Continuing Demolition

Click images for larger views

Looking at the garage demolition from the street
inside the construction demolition zone
Garage Demolition
Showing the "missing" levels

 

September 2010 -- Demolition

Click images for larger views

Demolition Equipment
Demolition in Progress
Looking at Courthouse
Aerial View of Demolition

 

Parking Garage RenderingPhase 1: Parking Garage

The new garage features 1,200 spaces, three elevator towers, three entrances, and a security office. The county kept its commitment to partnering with the borough to ensure an aesthetically pleasing yet functional design.

 

June 30, 2010 -- Ribbon Cutting

Phase One of the Bucks County Judicial Center construction project reached a sun-splashed conclusion this morning as Commissioner Chairman Charles H. Martin and Commissioner James F. Cawley, Esq. joined President Judge Susan D. Scott, Doylestown Borough officials and project contractors to cut the ribbon on the new Judicial Center Parking Garage. The 1,200-space, four-level facility is located between Union and Doyle streets, adjacent to Broad St. The $22-million garage required 18 months to complete, with the project coming in “on time, under budget, and with less than one-percent change orders,” in the words of Chairman Martin. (See more at: A Symbol of Commitment -- Commissioners Join President Judge to Cut Ribbon on 1,200-Space Judicial Center Parking Garage in Doylestown Borough)

Parking Garage Fact Sheet

Ribbon Cutting Audio

Images (click for larger size)
Doyle St
Parking Garage
Union and Broad Sts.
Inside
Lower Level

 

January 10, 2010 -- Ongoing Installation

Click images for larger views

Capstone
Close up of Capstone.
Stairs in Construction.
Installing Prefabricated Concrete.
Looking down from the top deck.
Completed concrete installation on the second level.
Crane on the top deck.
Exterior view of stairwell.
Exterior view of parking garage.
View from Union Street.
Top parking deck facing the Courthouse.
Exterior view.

 

November 17, 2009 -- Prefabricated Concrete Installation

Click images for larger views

Broad Street View of Construction

HookingColumnToCrane

LiftingColumnWithCrane

MovingColumnInPlace

InstallingColumn

InstallingAColumn

ColumnInstall

ViewNorthTowardsCourthouse

ViewFromRoofOfCourthouse

 

June 1, 2009 -- Construction Progress

Click images for larger views

Doyle Street View of Construction
Construction worker in a manhole
Construction worker down in manhole
Zoomed in view from courthouse roof.
Zoomed out view from Courthouse Roof
View of Old and New Garage
View of Old and New Garage, zoomed out
South wall of new garage
Construction of the garage

 

April 14, 2009 -- Ongoing Construction

Click images for larger views

Bulldozer in action
Construction at the Parking Garage Site

 

February 9, 2009 -- Early Construction

Click images for larger views

Construction, closer view
Construction, longshot view
Construction, view from the back

 

Groundbreaking December 22, 2008

Click images for larger views

Commissioner Martin
Judge Heckler
Commissioner Cawley
Crowd at groundbreaking
groundbreaking ceremony
2007 parking garage rendering

 

For more information, go to "Bucks County Commissioners, President Judge Break Ground on 1,200-Space Parking Garage: Frigid Kickoff to Phase I of Justice Center Project in Doylestown Borough"

Demolition and Clearing:

Click images for larger views

demolition of houses
Demoltion of garage site
tearing down a house
where the house once stood -- empty clearing
corner of broad and doyle, clear after demolition